Council insists Roscommon Town 'remains open for business' amid ongoing works
The disruption caused by public realm works in Roscommon Town has caused concern to traders and residents. Pic: Gerard O'Loughlin
Roscommon County Council has sought to reassure traders, residents and visitors that Roscommon town “remains fully open for business” as concerns continue over the impact of ongoing public realm works in the county town.
In a statement issued ahead of the Christmas shopping season, the local authority thanked businesses, residents and road users “for their patience” while work continues on the Roscommon Town Centre East Public Realm Enhancement Project.
The council said significant progress had been made in recent months and insisted that every effort is being made to ensure access to the town is maintained throughout the busy festive trading period.
The local authority stressed that temporary traffic management measures are intended to allow shoppers, visitors and residents to continue accessing the town safely while the regeneration project is being completed.
"Roscommon Town remains fully open for business," the council stated, adding that all public car parks in the town remain open and free of charge.
The council also appealed to the public to support local retailers and businesses over the Christmas and New Year period.
"The local authority encourages the public to continue supporting local businesses throughout the Christmas and New Year period and to enjoy all that Roscommon Town has to offer during the festive season," the statement said.
The response comes against a backdrop of concerns from some traders and residents regarding the disruption caused by the ongoing works and their potential impact on town centre footfall during one of the busiest trading periods of the year.
The council also issued a current update on the works:
1. Works Progressing Before Christmas
a. Athlone Road • Road carriageway resurfacing works are ongoing with road marking & ironwork adjustment to be completed.
• The Athlone Road will fully re-open to traffic on Saturday 28th November 2026.
b. Goff Street Lower • Goff Street Lower will re-open to traffic by close of business on this Monday 30 November with the new permanent one-way traffic arrangement coming into operation, with traffic travelling in the outbound direction from the town centre.
c. Henry Street • Henry Street will close on Tuesday 1st December 2026 to facilitate works on the project.
• The street will remain closed until 18th December 2026, when it will reopen for Christmas.
• Access to St Comans Church carpark will be maintained.
• Ongoing access for residents and arrangements for business deliveries will be maintained throughout the works.
d. Circular Road • Public realm works at various locations along Circular Road will continue up to 18th December 2026 with vehicular access being maintained at all times.
• Pedestrian access will be maintained on at least one side of the road, with signed crossing points provided where necessary.
• The new carpark at the rear of the Arts Centre is now fully open & available for use.
2. Christmas Shutdown Arrangements To support the Christmas trading period and minimise disruption, all construction activities within the town centre will cease from 18 December 2026 until 4 January 2027.
During this period:
• Unrestricted vehicular access to Main Street and The Square via Athlone Road and Goff Street will be available.
• Full pedestrian access throughout the town centre will be restored.
• Businesses, residents and visitors will be able to access the town centre as normal during the Christmas season.
3. Works Restart in January 2027 Works will recommence on 4th January 2027, with construction activities resuming at planned locations within the town centre as the project continues into its next phase.